Base material treatment: ensure that there is no oil or foreign matter on the base surface. For the powdering or peeling wall, it must be completely clean, and then sealed with special orbecci primer.
Construction tools: comb and scrape, universal brush, leather, roller, tree leather roller, etc.
Dilution: generally do not need to be diluted, if necessary, use water dilution, dilution amount control within 10%.
Construction environment: construction with temperature above 5℃ and relative humidity below 85%; Base water content<8%, can not be carried out outdoor construction in rainy days.
Clean: all tools should be cleaned with water immediately after use.
Safety matters:
To avoid contamination of skin and eyes or inhalation of excessive paint mist, please use protective equipment such as goggles, masks and gloves.
If skin has been contaminated, apply a neutral cleanser and warm water.
Keep out of reach of children.
Storage conditions: sealed storage in a cool dry place at 0-35℃.
Validity period: 18 months