Substrate treatment:
◎ build new walls - remove dirt, grease and loose marl from the surface. If there are pores, repair them in time to ensure the walls are clean, dry and smooth.
◎ heavy coating metope - remove the old wall paint film is not firm, remove dust powder and impurities, leveling, polishing, cleaning and thoroughly dry;
◎ ensure that the surface humidity of pre-coated substrate is 10% lower and the PH value is less than 10;
◎ the surface of pre-coated substrate must be firm, dry, clean, flat and free of loose matter.
Construction method: roller, brush and spray
Construction conditions: please do not operate in wet or cold weather (the temperature is lower than 5℃, the relative humidity is more than 85%), otherwise the expected effect cannot be achieved. Before construction, should mix coating even, besmear brusher - a form a complete set primer. Do not mix with other coatings.
Maintenance time: 7 days /25℃, low temperature (not less than 5℃) should be appropriately extended, in order to obtain the ideal paint film effect.
Dilution: according to the construction needs, add less than 5% of the water dilution; Stir well before use.
Cleaning: please wash all the appliances with water immediately after the painting stops or finishes.
Storage conditions: sealed storage in a cool dry place at 0-35℃.
Validity period: 18 months
Execution standard: GB/T 9755-2001